M/S. Zeus Engitech Private Limited has taken the successful load trial of the first stream of salt washery plant up to the attached conveyor dated 23.05.2019. They took a successful load trial of the first stream at 200 TPH feed rate along with the tripper and boom conveyor of the Salt Washery plant dated 04.01.2020. They also had taken the successful load trial of the second stream of salt washery plant on dated 17.02.2020. As per SBPL’s requirement and purchase order, the load trial concluded. M/s. SBPL started production of salt from 5 Jan 2020 to 19h March 2020 and resumed production from 19 May 2020 would also like to inform you that during the production period, we didn’t notice any problems regarding the plant. All safety points guided are through the safety department of M/s. SBPL has been resolved/closed. After installation of the third stream, all the mechanical work, including roof structure and sheeting work done as per SBPL’s requirement. In future, during the third stream will be installed, the top roof and only the dismantaltion of truss has to done after, that only we will be doing erection of equipment can be done. Since all work has been completed and as M/S. SBPL want to start their salt production again, henceforth now dated 28.01.2021 M/s. ZEPL would like to hand over the salt washery plant to M/S. SBPL and request the get commissioning certificate from M/s SBPL.